Conflict continues in the mining sector and is drawing in increasing efforts from the government to try to work with all parties to resolve the issues. Three of the country’s largest projects are currently involved in difficult disputes, with production now suspended at Las Bambas. Production is set to begin again at Cuajone following state mediation but the situation remains tense. Together these two mines account for about 20% of Peru’s copper output.

Las Bambas is the huge copper and gold mine in Apurímac region supplying 2% of the world’s copper and owned by China’s MMG. The development stage of the project involved resettlement of the local community of Fuerabamba. The community is now protesting at what it sees as the company’s failure to comply with its commitments to social investment made as part of the resettlement deal. A meeting on 16 April between the community, the company, and the Ministry of Energy and Mines (Minem) failed to reach agreement and further meetings are planned by the Prime Minister’s Office (PCM).

On 20 April, MMG announced that it was suspending production at the mine following the occupation by 200 community members of land that previously belonged to Fuerabamba. Community members say that MMG has failed to honour commitments made in return for relinquishing their land. According to one of their representatives, quoted by La República, it is “thanks to us [that] Las Bambas exists, we have given everything for mining and now we regret having given up our lands”. The company denies failing to comply with agreements. A dialogue round table is due to take place on 25 and 26 April, but as of 22 April community members were constructing houses on the land in dispute.

In Espinar, Cuzco region, the conflict centres on the mine Coroccohuayco owned by Antapaccay, a subsidiary of Glencore plc. The Ministry of the Environment is currently in dialogue with eleven communities that want to be included in the group of those specifically affected by the project and therefore eligible for compensation. Local communities fear that the project will pollute their environment in similar form to what happened with Glencore’s nearby Tintaya operation. Communities last week were planning strike action with possible roadblocks interrupting access to and from the mine.

At Southern Peru Copper’s project at Cuajone, the conflict appears to have been temporarily settled following the declaration of a state of emergency and the deployment of police to the mine. Community members had taken control of the reservoir supplying water to the mining encampment. According to Prime Minister Aníbal Torres, quoted by Reuters, the government had been “running out of patience” and the communities were demanding “something irrational, $5 billion”. The dispute, which began on 18 February, led to the suspension of production and the loss of around US$4.5 million a day. Mineworkers last week threatened to confront community members, illustrating once again the divergent agendas of the various social groups involved in and around mining camps.

The companies affected believe that the government is giving priority to the right to protest over their concerns about the ability freely to mine and transport minerals to port.